Overview

Timeline:Milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release. Due to KS needs and ARC Approval, the scope of 2.3 was split into 2.3 and 2.4.

Split: ~ 70% new features/30% maintenance

Scope & Tasks

See working 2.3 Project Plan spreadsheet for task breakdown, tracking, and progress.

Roadmap Items

  1. KRRM-144: KRAD Equivalency with KNS: delivered in 2.4, some items will be delivered in 2.3.
  2. KRRM-141: KRAD Phase 3: 1000 hours; remaining items in 2.4
  3. KRRM-143: Update delivered Rice Screens to use KRAD: delivered in 2.4, some screen conversions may be delivered in 2.3
  4. KRRM-1: Implement JPA: delivered in 2.4

See Rice 2.3 Design and Analysis and Rice 2.4 Design and Analysis pages for more detailed analysis of Roadmap items.

Resources

Parallel Team Model: 2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources

Teams

Claus Niesen (DM)

Samuel Holtzkampf

Steve Manning

Martin Taylor

Shannon Hess

Peter Giles (DM)

Brian Smith

Jeff Ruch

Sona Muthuswamy

Corey Pedersen

Matthew Wuertz

Erik Meade (Lead)

Dan Seibert

Deep Moteria

Eric Westfall (LTA)

Aaron Hamid

Jonathan Keller

Jessica Coltrin (PM)

Jerry Neal (KRAD Architect)

Functional Team: Matt Sargent (BA), Tom Clark (UX), Grant Trudel (TW)

Responsibilities

Milestones

2.3 Milestone 1 Release - April 8, 2013

2.3 Milestone 2 Release - May 6, 2013

2.3 Milestone 3 Release - June 24, 2013

2.3 Release Candidate 1 - July 8, 2013

2.3 Final Release - July 31, 2013


2.4 Milestone 1 Release - August 12, 2013

2.4 Milestone 2 - September 16, 2013

2.4 Milestone 3 - October 14, 2013

2.4 Final Release - February 15, 2014


2.5 Final Release - August 2014