Scope & Tasks
See working 2.4 Agile Planning Board for task breakdown, tracking, and progress.
Items






















(possibly out of scope)
See Rice 2.4 Design and Analysis pages for more detailed analysis of Roadmap items.
Milestones
2.4 Milestone 1 - August 12, 2013 - complete
Scope:
- JPA: Data Layer Restructuring, some Internal JPA Conversion

Sprints:
- JPA Sprint 1
- JPA Sprint 2
- JPA Sprint 3
- JPA Sprint 4
- JPA Sprint 5
2.4 Milestone 2 - October 15, 2013 - complete
Scope:
- KRAD/KNS Equivalency:
- Lookup Gap Analysis complete (Phases 1 & 2 - identification of items & if they're already covered in KRAD)

- Inquiry Gap Analysis complete for Inquiry

- Maintenance Gap Analysis complete for Maintenance

- Lookup Equivalency achieved (jiras done)
- Lookup Conversion Guide draft complete
- Lookup Phase 3 Analysis (focus group preparation & review)

- JPA:
- Internal conversion of KEW to JPA

- "Defaulting" features for inquiries, lookups, etc. (needed for demo at Kuali Days!)

- KRAD Phase 3:
- Performance tuning goals for response time

- UXI
- Application Header
- New Left Menu
- Form Control redesign
- Input Groups
- Label Align CSS Grid
- Styling improvements: View Header, Sticky Footer, Tabs, Disclosures, Dialogs
- QA:
Sprints:
2.4 Milestone 3 - December 17, 2013 - complete
Scope:
- KRAD/KNS Equivalency:
- JPA:
- eDocLite converted to JPA

- KSB converted to JPA

- Basic documentation on how to convert OJB to JPA

- Conversion scripts for OJB to JPA
- KRAD Phase 3:
- Performance: DOM cleanup & memory work
- Implement DevOps Database Process Changes
- QA:
- Formalize strategy for JPA testing
- Establish performance testing plan
- AFT Gap Analysis: Continue with gap analysis on granular level to confirm that existing tests perform as they should
- Continued JIRA backlog grooming

- Close manually-testable Resolved jiras

- Continue to fill AFT gaps (with JPA testing strategy in mind)

- KD Prep

Sprints:
- 2.4.0-m3 Sprint 1
- 2.4.0-m3 Sprint 2
- 2.4.0-m3 Sprint 3
- 2.4.0-m4 Sprint 4
2.4 Milestone 4 - February 19, 2014 - complete
Scope:
- KRAD/KNS Equivalency:
- Focus Groups for Components
- Finish Conversion Script & Guide for 2.4

- Work on non-UXI gap items

- JPA:
- KIM, KRMS,KEN Converted to JPA

- Conversion script documentation

- Mostly completed Documentation
- QA:
- Establish performance testing plan

- Set up dedicated performance test environment

Sprints:
- 2.4.0-m4 Sprint 1
- 2.4.0-m4 Sprint 2
- 2.4.0-m4 Sprint 3
- 2.4.0-m4 Sprint 4
2.4 Final Release - April 18, 2014
Scope:
- Complete Regression Testing
- Complete Unit & Integration Tests
- Complete Performance Testing
- Complete Documentation