Overview

Timeline:Milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release. Original scope for 2.3 has been split into 3 minor releases: Rice 2.3, Rice 2.4, and Rice 2.5.

Split: ~ 70% new features/30% maintenance

Scope & Tasks

See working 2.3 Project Plan spreadsheet for task breakdown, tracking, and progress. Original scope for 2.3 has been split into 3 minor releases: Rice 2.3, Rice 2.4, and Rice 2.5.

Roadmap Items

  1. KRRM-141: KRAD Phase 3: top 5 items

See Rice 2.3 Design and Analysis page for more detailed analysis of Roadmap items.

Resources

Parallel Team Model: 2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources

Teams

Claus Niesen (DM)

Samuel Holtzkampf

Steve Manning

Martin Taylor

Shannon Hess

Peter Giles (DM)

Brian Smith

Jeff Ruch

Sona Muthuswamy

Corey Pedersen

Matthew Wuertz

Erik Meade (Lead)

Dan Seibert

Deep Moteria

Eric Westfall (LTA)

Aaron Hamid

Jonathan Keller

Jessica Coltrin (PM)

Jerry Neal (KRAD Architect)

Functional Team: Matt Sargent (BA), Tom Clark (UX), Grant Trudel (TW)

Responsibilities

Milestones

2.3 Milestone 1 Release - April 8, 2013

2.3 Milestone 2 Release - May 6, 2013

2.3 Milestone 3 Release - June 24, 2013

2.3 Release Candidate 1 - July 8, 2013

2.3 Final Release - July 31, 2013