Overview

Timeline:Milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release. Due to KS needs and ARC Approval, the scope of 2.3 was split into 2.3 and 2.4.

Split: ~ 70% new features/30% maintenance

Scope & Tasks

See working 2.3 Project Plan spreadsheet for task breakdown, tracking, and progress.

Roadmap Items

  1. KRRM-144: KRAD Equivalency with KNS: delivered in 2.4, some items will be delivered in 2.3.
  2. KRRM-141: KRAD Phase 3: 1000 hours; remaining items in 2.4
  3. KRRM-143: Update delivered Rice Screens to use KRAD: delivered in 2.4, some screen conversions may be delivered in 2.3
  4. KRRM-1: Implement JPA: delivered in 2.4

See Rice 2.3 Design and Analysis and Rice 2.4 Design and Analysis pages for more detailed analysis of Roadmap items.

Resources

Parallel Team Model: 2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources

Teams

Responsibilities

  • KNS Equivalency - Red Team, Jerry (some), Jonathan (analysis)
  • Rice Conversion, KRAD Phase 3 - Blue Team, Jerry (some)
  • JPA - JPA Team
  • 2.3 Maintenance Items - Jerry, others as needed
  • Testing, Performance Benchmarking - QA Team
  • Documentation Updates, Conversion Guide - Grant
  • KRAD Look & Feel, Screen Mocks/UX - Tom
  • Project Schedule/Coordination - Jessica
  • Requirements Prioritization & Analysis - Matt

Milestones

2.3 Milestone 1 Release - April 8, 2013

  • Screen Conversion: Misc. Cleanup, start on items delivered in m2
  • Phase 3: Page Titling redesign, Back button support for js actions, Iterate on validation framework UI (priority #2,5,6); Note that Breadcrumbs was postponed due to delays in requirements from KS

2.3 Milestone 2 Release - May 6, 2013

  • KRAD/KNS Equivalency: Session Support
  • Screen Conversion: Login Page
  • Phase 3: KULRICE-8630 (History and Breadcrumbs), Improved Session Support, some performance enhancements including lite table

2.3 Milestone 3 Release - June 24, 2013

  • KRAD/KNS Equivalency: Lookup (except Multi-Value Lookup) 
  • Screen Conversion: Action List
  • Phase 3: Improve Performance & Memory Consumption (priority #1,3,4)
  • Inclusion of Bootstrap & LESS

2.3 Release Candidate 1 - July 8, 2013

  • Bootstrap/LESS themes
  • Tier 2 Performance Enhancements

2.3 Final Release - July 31, 2013

  • Regression Testing 
  • Testing & Documentation of new Features
  • Bug Fixes

2.4 Milestone 1 Release - August 12, 2013

  • KRAD/KNS Equivalency: Multi-value Lookup , Inquiry gap analysis, Finish Removing Struts, Module Support (MVC), Inquiry, Maintenance gap analysis, Components/Collections,Security, Presentation and Authorizer
  • Phase 3:
  • JPA: Data Layer Restructuring, Internal JPA Conversion, JPA Conversion Support

2.4 Milestone 2 - September 16, 2013

  • KRAD/KNS Equivalency: Maintenance (incl. conversion guide and script), Transactional gap analysis
  • Screen Conversion: Administration - Identity, Configuration

2.4 Milestone 3 - October 14, 2013

  • KRAD/KNS Equivalency: Transactional(incl. conversion guide and script), Complete Draft of Conversion Scripts & Guide
  • Online Help integrated with DocBook & documented for project use

2.4 Final Release - February 15, 2014

  • Regression Testing
  • Complete Unit & Integration Tests
  • Complete Performance Testing
  • Complete Documentation

2.5 Final Release - August 2014

  • screen conversions