Overview

Timeline:Milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release. Due to KS needs and ARC Approval, the scope of 2.3 was split into 2.3 and 2.4.

Split: ~ 70% new features/30% maintenance

Roadmap Items

  1. KRRM-144: KRAD Equivalency with KNS: delivered in 2.4, some items will be delivered in 2.3.
  2. KRRM-141: KRAD Phase 3: 1000 hours; remaining items in 2.4
  3. KRRM-143: Update delivered Rice Screens to use KRAD: delivered in 2.4, some screen conversions may be delivered in 2.3
  4. KRRM-1: Implement JPA: delivered in 2.4

See Rice 2.3 Design and Analysis and Rice 2.4 Design and Analysis pages for more detailed analysis of Roadmap items.

See working 2.3 Project Schedule for task breakdown and detailed estimates.

Maintenance Items

  • Regression Testing
  • Critical Bug Fixing, Reviewing & Incorporating Contributions
  • Updating Outdated Documentation
  • Gap Analysis with KC & KFS on KNS/KRAD

Total: 2380 Hours

Bigger Maintenance Issues

KULRICE-7998

KULRICE-7991

KULRICE-8630

KULRICE-8631

Parallel Team Model

2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources

Teams

Responsibilities

  • KNS Equivalency - Red Team, Jerry (some), Jonathan (analysis)
  • Rice Conversion, KRAD Phase 3 - Blue Team, Jerry (some)
  • JPA - JPA Team
  • 2.3 Maintenance Items - Jerry, others as needed
  • Testing, Performance Benchmarking - QA Team
  • Documentation Updates, Conversion Guide - Grant
  • KRAD Look & Feel, Screen Mocks/UX - Tom
  • Project Schedule/Coordination - Jessica
  • Requirements Prioritization & Analysis - Matt

Milestones

2.3 Milestone 1 Release - April 8, 2013

  • Screen Conversion: Misc. Cleanup, start on items delivered in m2
  • Phase 3: Page Titling redesign, Back button support for js actions, Iterate on validation framework UI (priority #2,5,6); Note that Breadcrumbs was postponed due to delays in requirements from KS

2.3 Milestone 2 Release - May 6, 2013

  • KRAD/KNS Equivalency: Session Support
  • Screen Conversion: Login Page, Action List
  • Phase 3: KULRICE-8630 (History and Breadcrumbs), Improved Session Support, some performance enhancements including lite table

2.3 Milestone 3 Release - June 10, 2013

  • KRAD/KNS Equivalency: Lookup & Multi-value Lookup (incl. conversion guide and script), Inquiry gap analysis, Finish Removing Struts, Module Support (MVC)
  • Screen Conversion: Main Menu - Sample Travel Application Channel, Workflow, Notification, Document Search
  • Phase 3: Improve Performance & Memory Consumption (priority #1,3,4)
  • Bootstrap & LESS

2.3 Final Release - July 31, 2013

  • Regression Testing 
  • Testing & Documentation of new Features

2.4 Milestone 1 Release - August 12, 2013

  • KRAD/KNS Equivalency: Inquiry (incl. conversion guide and script), Maintenance gap analysis, Components/Collections,Security, Presentation and Authorizer
  • Phase 3:
  • Screen Conversion: Main Menu - KRMS Rules, Administration - Workflow, Notification
  • JPA: Data Layer Restructuring, Internal JPA Conversion, JPA Conversion Support

2.4 Milestone 2 - September 16, 2013

  • KRAD/KNS Equivalency: Maintenance (incl. conversion guide and script), Transactional gap analysis
  • Screen Conversion: Administration - Identity, Configuration

2.4 Milestone 3 - October 14, 2013

  • KRAD/KNS Equivalency: Transactional(incl. conversion guide and script), Complete Draft of Conversion Scripts & Guide
  • Screen Conversion: Administration - Service Bus, Miscellaneous
  • Online Help integrated with DocBook & documented for project use

2.4 Final Release - November 1, 2013

  • Regression Testing
  • Complete Unit & Integration Tests
  • Complete Performance Testing
  • Complete Documentation