Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 65 Next »

Overview

Timeline:Milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release. Due to KS needs and ARC Approval, the scope of 2.3 was split into 2.3 and 2.4.

Split: ~ 70% new features/30% maintenance

Roadmap Items

  1. KRRM-144: KRAD Equivalency with KNS: delivered in 2.4, some items will be delivered in 2.3.
  2. KRRM-141: KRAD Phase 3: 1000 hours; remaining items in 2.4
  3. KRRM-143: Update delivered Rice Screens to use KRAD: delivered in 2.4, some screen conversions may be delivered in 2.3
  4. KRRM-1: Implement JPA: delivered in 2.4

See Rice 2.3 Design and Analysis and Rice 2.4 Design and Analysis pages for more detailed analysis of Roadmap items.

See working 2.3 Project Schedule for task breakdown and detailed estimates.

Maintenance Items

  • Regression Testing
  • Critical Bug Fixing, Reviewing & Incorporating Contributions
  • Updating Outdated Documentation
  • Gap Analysis with KC & KFS on KNS/KRAD

Total: 2380 Hours

Bigger Maintenance Issues

KULRICE-7998

KULRICE-7991

KULRICE-8630

KULRICE-8631

Parallel Team Model

2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources

Teams

Responsibilities

  • KNS Equivalency - Red Team, Jerry (some), Jonathan (analysis)
  • Rice Conversion, KRAD Phase 3 - Blue Team, Jerry (some)
  • JPA - JPA Team
  • 2.3 Maintenance Items - Jerry, others as needed
  • Testing, Performance Benchmarking - QA Team
  • Documentation Updates, Conversion Guide - Grant
  • KRAD Look & Feel, Screen Mocks/UX - Tom
  • Project Schedule/Coordination - Jessica
  • Requirements Prioritization & Analysis - Matt

Milestones

2.3 Milestone 1 Release - April 8, 2013

  • KRAD/KNS Equivalency: Lookup (except multi-value lookup)
  • Screen Conversion: Misc. Cleanup, start on items delivered in m2
  • Phase 3: Page Titling redesign, Back button support for js actions, Iterate on validation framework UI (priority #2,5,6); Note that Breadcrumbs was postponed due to delays in requirements from KS

2.3 Milestone 2 Release - May 6, 2013

  • KRAD/KNS Equivalency: Conversion Script Lookup, Session Support
  • Screen Conversion: Login Page, Action List
  • Phase 3: KULRICE-8630 (History and Breadcrumbs), Improved Session Support, some performance enhancement

2.3 Milestone 3 Release - June 10, 2013

  • KRAD/KNS Equivalency: Transactional, Conversion Script Inquiry/Maintenance, Finish Removing Struts, Components/Collections, Module Support (MVC), Security, Presentation and Authorizer, Inquiry, Maintenance, Multi-value lookup
  • Screen Conversion: Main Menu - Sample Travel Application Channel, Workflow, Notification, Document Search
  • Phase 3: Improve Performance & Memory Consumption (priority #1,3,4)

2.3 Final Release - July 31, 2013

  • Regression Testing 
  • Testing & Documentation of new Features

2.4 Milestone 1 Release - August 12, 2013

  • KRAD/KNS Equivalency: Conversion Script Transactional, Complete Draft of Conversion Scripts & Guide
  • Phase 3:
  • Screen Conversion: Main Menu - KRMS Rules, Administration - Workflow, Notification
  • JPA: Data Layer Restructuring, Internal JPA Conversion, JPA Conversion Support

2.4 Milestone 2 - September 16, 2013

  • Screen Conversion: Administration - Identity, Configuration

2.4 Milestone 3 - October 14, 2013

  • Screen Conversion: Administration - Service Bus, Miscellaneous
  • Online Help integrated with DocBook & documented for project use

2.4 Final Release - November 1, 2013

  • Regression Testing
  • Complete Unit & Integration Tests
  • Complete Performance Testing
  • Complete Documentation
  • No labels