- Overview
- Roadmap Items
- Maintenance Items
- Parallel Team Model
- Responsibilities
- Milestones
- 2.3 Milestone 1 Release - April 8, 2013
- 2.3 Milestone 2 Release - May 6, 2013
- 2.3 Milestone 3 Release - June 10, 2013
- 2.3 Final Release - July 31, 2013
- 2.4 Milestone 1 Release - August 12, 2013
- 2.4 Milestone 2 - September 16, 2013
- 2.4 Milestone 3 - October 14, 2013
- 2.4 Final Release - November 1, 2013
Overview
Timeline:Milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release. Due to KS needs and ARC Approval, the scope of 2.3 was split into 2.3 and 2.4.
Split: ~ 70% new features/30% maintenance
Roadmap Items
- KRRM-144: KRAD Equivalency with KNS: delivered in 2.4, some items will be delivered in 2.3.
- KRRM-141: KRAD Phase 3: 1000 hours; remaining items in 2.4
- KRRM-143: Update delivered Rice Screens to use KRAD: delivered in 2.4, some screen conversions may be delivered in 2.3
- KRRM-1: Implement JPA: delivered in 2.4
See Rice 2.3 Design and Analysis and Rice 2.4 Design and Analysis pages for more detailed analysis of Roadmap items.
See working 2.3 Project Schedule for task breakdown and detailed estimates.
Maintenance Items
- Regression Testing
- Critical Bug Fixing, Reviewing & Incorporating Contributions
- Updating Outdated Documentation
- Gap Analysis with KC & KFS on KNS/KRAD
Total: 2380 Hours
Bigger Maintenance Issues
KULRICE-7998
KULRICE-7991
KULRICE-8630
KULRICE-8631
Parallel Team Model
2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources
Teams
Erik Meade (Lead) |
Jessica Coltrin (PM) |
Jerry Neal (KRAD Architect) |
Functional Team: Matt Sargent (BA), Tom Clark (UX), Grant Trudel (TW) |
Responsibilities
- KNS Equivalency - Red Team, Jerry (some), Jonathan (analysis)
- Rice Conversion, KRAD Phase 3 - Blue Team, Jerry (some)
- JPA - JPA Team
- 2.3 Maintenance Items - Jerry, others as needed
- Testing, Performance Benchmarking - QA Team
- Documentation Updates, Conversion Guide - Grant
- KRAD Look & Feel, Screen Mocks/UX - Tom
- Project Schedule/Coordination - Jessica
- Requirements Prioritization & Analysis - Matt
Milestones
2.3 Milestone 1 Release - April 8, 2013
- KRAD/KNS Equivalency: Lookup (except multi-value lookup)
- Screen Conversion: Misc. Cleanup, start on items delivered in m2
- Phase 3: Page Titling redesign, Back button support for js actions, Iterate on validation framework UI (priority #2,5,6); Note that Breadcrumbs was postponed due to delays in requirements from KS
- JPA: Data Layer Restructuring
2.3 Milestone 2 Release - May 6, 2013
- KRAD/KNS Equivalency: Multi-value lookup, Inquiry, Maintenance, Conversion Script Lookup, Security, Presentation and Authorizer, Session Support
- Screen Conversion: Login Page, Document Search, Action List
- Phase 3: KULRICE-8630 (History and Breadcrumbs), Improved Session Support, Improve Performance & Memory Consumption (priority #1,3,4)
- JPA: Internal JPA Conversion, JPA Conversion Support
2.3 Milestone 3 Release - June 10, 2013
- KRAD/KNS Equivalency: Transactional, Conversion Script Inquiry/Maintenance, Finish Removing Struts, Components/Collections, Module Support (MVC)
- Screen Conversion: Main Menu - Sample Travel Application Channel, Workflow, Notification
- Phase 3:
- JPA: Test & Merge JPA code
2.3 Final Release - July 31, 2013
- Regression Testing
- Testing & Documentation of new Features
2.4 Milestone 1 Release - August 12, 2013
- KRAD/KNS Equivalency: Conversion Script Transactional, Complete Draft of Conversion Scripts & Guide
- Phase 3:
- Screen Conversion: Main Menu - KRMS Rules, Administration - Workflow, Notification
2.4 Milestone 2 - September 16, 2013
- Screen Conversion: Administration - Identity, Configuration
2.4 Milestone 3 - October 14, 2013
- Screen Conversion: Administration - Service Bus, Miscellaneous
- Online Help integrated with DocBook & documented for project use
2.4 Final Release - November 1, 2013
- Regression Testing
- Complete Unit & Integration Tests
- Complete Performance Testing
- Complete Documentation