- Overview
- Roadmap Items
- Maintenance Items
- Parallel Team Model
- Responsibilities
- Milestones
- 2.3 Milestone 1 Release - April 8, 2013
- 2.3 Milestone 2 Release - May 6, 2013
- 2.3 Milestone 3 Release - June 10, 2013
- 2.3 Final Release - July 31, 2013
- 2.4 Milestone 1 Release - August 12, 2013
- 2.4 Milestone 2 - September 16, 2013
- 2.4 Milestone 3 - October 14, 2013
- 2.4 Final Release - November 1, 2013
Overview
Timeline:Milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release. Due to KS needs and ARC Approval, the scope of 2.3 was split into 2.3 and 2.4.
Split: ~ 70% new features/30% maintenance
Roadmap Items
- KRRM-144: KRAD Equivalency with KNS: delivered in 2.4, some items will be delivered in 2.3.
- KRRM-141: KRAD Phase 3: 1000 hours; remaining items in 2.4
- KRRM-143: Update delivered Rice Screens to use KRAD: delivered in 2.4, some screen conversions may be delivered in 2.3
- KRRM-1: Implement JPA: delivered in 2.4
See Rice 2.3 Design and Analysis page for more detailed analysis of Roadmap items.
See working 2.3 Project Schedule for task breakdown and detailed estimates.
Maintenance Items
- Regression Testing
- Critical Bug Fixing, Reviewing & Incorporating Contributions
- Updating Outdated Documentation
- Gap Analysis with KC & KFS on KNS/KRAD
Total: 2380 Hours
Bigger Maintenance Issues
KULRICE-7998
KULRICE-7991
KULRICE-8630
KULRICE-8631
Parallel Team Model
2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources
Teams
Erik Meade (Lead) |
Jessica Coltrin (PM) |
Jerry Neal (KRAD Architect) |
Functional Team: Matt Sargent (BA), Tom Clark (UX), Grant Trudel (TW) |
Responsibilities
- KNS Equivalency - Red Team, Jerry (some), Jonathan (analysis)
- Rice Conversion, KRAD Phase 3 - Blue Team, Jerry (some)
- JPA - JPA Team
- 2.3 Maintenance Items - Jerry, others as needed
- Testing, Performance Benchmarking - QA Team
- Documentation Updates, Conversion Guide - Grant
- KRAD Look & Feel, Screen Mocks/UX - Tom
- Project Schedule/Coordination - Jessica
- Requirements Prioritization & Analysis - Matt
Milestones
2.3 Milestone 1 Release - April 8, 2013
- KRAD/KNS Equivalency: Lookup, Inquiry Gap analysis, Session Support
- Screen Conversion: Login Page, Document Search, Action List, Help (not needed since KRAD does help differently)
- Phase 3: KULRICE-8630 (History and Breadcrumbs)
- JPA: Data Layer Restructuring
2.3 Milestone 2 Release - May 6, 2013
- KRAD/KNS Equivalency: Inquiry, Maintenance, Conversion Script Lookup, Security, Presentation and Authorizer
- Screen Conversion: Main Menu - Sample Travel Application Channel, Workflow, Notification
- Phase 3:
- JPA: Internal JPA Conversion, JPA Conversion Support
2.3 Milestone 3 Release - June 10, 2013
- KRAD/KNS Equivalency: Transactional, Conversion Script Inquiry/Maintenance, Finish Removing Struts, Components/Collections, Module Support (MVC)
- Screen Conversion: Main Menu - KRMS Rules, Administration - Workflow, Notification
- Phase 3:
- JPA: Test & Merge JPA code
2.3 Final Release - July 31, 2013
- Regression Testing
- Testing & Documentation of new Features
2.4 Milestone 1 Release - August 12, 2013
- KRAD/KNS Equivalency: Conversion Script Transactional, Complete Draft of Conversion Scripts & Guide
- Phase 3:
- Screen Conversion: Administration - Identity, Configuration
2.4 Milestone 2 - September 16, 2013
- Screen Conversion: Administration - Service Bus, Miscellaneous
2.4 Milestone 3 - October 14, 2013
2.4 Final Release - November 1, 2013
- Regression Testing
- Complete Unit & Integration Tests
- Complete Performance Testing
- Complete Documentation