Overview
Timeline: Proposed 6 month release (~ 1/15/13-7/15/13) with milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release.
Split: ~ 70% new features/30% maintenance
Roadmap Items
- KRRM-144: KRAD Equivalency with KNS: 500 hours
- KRRM-141: KRAD Phase 3: 1000 hours
- KRRM-143: Update delivered Rice Screens to use KRAD: 1000 hours
- KRRM-1: Implement JPA: 1000 hours
Roadmap Analysis & Development Hours: 3500
Gap Analysis with KC & KFS on KNS/KRAD: 400 hours
Documentation, Testing, Bug Fixing: 2380 hours (1600 dev hours, 780 QA hours)
Total: 6280 hours
See Rice 2.3 Design and Analysis page for more detailed analysis of Roadmap items.
See working 2.3 Project Schedule for task breakdown and detailed estimates.
Maintenance Items
- Regression Testing (780 QA hours)
- Critical Bug Fixing, Reviewing & Incorporating Contributions (1600 Development Hours)
- Updating Outdated Documentation (TBD when tech writer is hired)
Total: 2380 Hours
Bigger Maintenance Issues
KULRICE-7998
KULRICE-7991
KULRICE-8630
KULRICE-8631
Parallel Team Model
2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources
Teams
Erik Meade (Lead) |
Jessica Coltrin (PM) |
Functional Team: Matt Sargent (BA), Tom Clark (UX), Grant Trudel (TW) |
Roadmap Work Breakdown
KNS Equivalency
Red Team, Jerry (some), Jonathan (some)
Rice Conversion, KRAD Phase 3
Blue Team, Jerry (some)
JPA
JPA Team
Milestones
Milestone 1 Release - March 4, 2013
- KRAD/KNS Equivalency: Lookup, Inquiry, Session Support
- Screen Conversion: Login Page, Document Search, Action List, Help
- Phase 3:
- Maintenance (Big): KULRICE-8630 (History and Breadcrumbs)
- JPA: Data Layer Restructuring
Milestone 2 Release - April 8, 2013
- KRAD/KNS Equivalency: Maintenance, Transactional, Security, Presentation and Authorizer
- Screen Conversion: Main Menu - Sample Travel Application Channel, Workflow, Notification
- Phase 3:
- Maintenance (Big):
- JPA: Internal JPA Conversion, JPA Conversion Support
Milestone 3 Release - May 6, 2013
- KRAD/KNS Equivalency: Finish Removing Struts, Components/Collections, Module Support (MVC)
- Screen Conversion: Main Menu - KRMS Rules, Administration - Workflow, Notification
- Phase 3:
- Maintenance (Big):
- JPA: Test & Merge JPA code
Milestone 4 Release - June 10, 2013
- KRAD/KNS Equivalency: Complete Draft of Conversion Scripts & Guide
- Phase 3:
- Maintenance (Big):
- Screen Conversion: Administration - Identity, Configuration
Milestone 5 - July 8, 2013
- Screen Conversion: Administration - Service Bus, Miscellaneous
Milestone 6 - August 12, 2013
Milestone 7 - September 16, 2013
RC1 Release - October 14, 2013
- Complete Unit & Integration Tests
- Complete Performance Testing