Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 37 Next »

Overview

Timeline: Proposed 6 month release (~ 1/15/13-7/15/13) with milestones every 4-5 weeks or so.

Split: ~ 70% new features/30% maintenance

Roadmap Items

  1. KRRM-144: KRAD Equivalency with KNS: 500 hours
  2. KRRM-141: KRAD Phase 3: 1000 hours
  3. KRRM-143: Update delivered Rice Screens to use KRAD: 1000 hours
  4. KRRM-1: Implement JPA: 1000 hours

Roadmap Analysis & Development Hours: 3500
Gap Analysis with KC & KFS on KNS/KRAD: 400 hours
Documentation, Testing, Bug Fixing: 2380 hours (1600 dev hours, 780 QA hours)
Total: 6280 hours

See Rice 2.3 Design and Analysis page for more detailed analysis of Roadmap items.

See working 2.3 Project Schedule for task breakdown and detailed estimates.

Maintenance Items

  • Regression Testing (780 QA hours)
  • Critical Bug Fixing, Reviewing & Incorporating Contributions (1600 Development Hours)
  • Updating Outdated Documentation (TBD when tech writer is hired)

Total: 2380 Hours

Bigger Maintenance Issues

KULRICE-7998

KULRICE-7991

KULRICE-8630

KULRICE-8631

Parallel Team Model

2 Development Teams, 1 QA Team, & Shared Resources

Teams

Shared Resources

Jessica Coltrin (PM)

Architecture Team: Eric Westfall (LTA), Jerry Neal (KRAD Architect)

Functional Team: Matt Sargent (BA), Tom Clark (UX), Grant Trudel (TW)

Roadmap Work Breakdown 

KNS Equivalency

Claus, Samuel, Steve, Martin, Shannon, Jerry (some), Jonathan (some)

KRAD Phase 3

Brian

Rice Conversion

Peter, Jeff, Sona, Corey, Matt W., Jerry (some)

JPA

Eric, Jerry (some), Jonathan (some), Aaron

Milestones

Milestone 1 Release - March 4, 2013

  • KRAD/KNS Equivalency: Lookup, Inquiry, Session Support
  • Screen Conversion: Login Page, Document Search, Action List, Help
  • Phase 3: 
  • Maintenance (Big): KULRICE-8630 (History and Breadcrumbs)
  • JPA: Data Layer Restructuring

Milestone 2 Release - April 8, 2013

  • KRAD/KNS Equivalency: Maintenance, Transactional, Security, Presentation and Authorizer
  • Screen Conversion: Main Menu - Sample Travel Application Channel, Workflow, Notification
  • Phase 3:
  • Maintenance (Big):
  • JPA: Internal JPA Conversion, JPA Conversion Support

Milestone 3 Release - May 6, 2013

  • KRAD/KNS Equivalency: Finish Removing Struts, Components/Collections, Module Support (MVC)
  • Screen Conversion: Main Menu - KRMS Rules, Administration - Workflow, Notification
  • Phase 3:
  • Maintenance (Big):
  • JPA: Test & Merge JPA code

Milestone 4 Release - June 10, 2013

  • KRAD/KNS Equivalency: Complete Draft of Conversion Scripts & Guide
  • Phase 3:
  • Maintenance (Big):
  • Screen Conversion: Administration - Identity, Configuration

Milestone 5 - July 8, 2013

  • Screen Conversion: Administration - Service Bus, Miscellaneous

Milestone 6 - August 12, 2013

Milestone 7 - August 12, 2013

RC1 Release - October 14, 2013

  • Complete Unit & Integration Tests
  • Complete Performance Testing

Final Release - November 1, 2013

  • No labels