Overview

Timeline: Proposed 6 month release (~ 1/15/13-7/15/13) with milestones every 4-5 weeks or so.

Split: ~ 70% new features/30% maintenance

Roadmap Items

  1. KRRM-144: KRAD Equivalency with KNS: 500 hours
  2. KRRM-141: KRAD Phase 3: 1000 hours
  3. KRRM-143: Update delivered Rice Screens to use KRAD: 1000 hours
  4. KRRM-1: Implement JPA: 1000 hours

Roadmap Analysis & Development Hours: 3500
Gap Analysis with KC & KFS on KNS/KRAD: 400 hours
Documentation, Testing, Bug Fixing: 2380 hours (1600 dev hours, 780 QA hours)
Total: 6280 hours

See Rice 2.3 Design and Analysis page for more detailed analysis of Roadmap items.

Maintenance Items

  • Regression Testing (780 QA hours)
  • Critical Bug Fixing, Reviewing & Incorporating Contributions (1600 Development Hours)
  • Updating Outdated Documentation (TBD when tech writer is hired)

Total: 2380 Hours

Parallel Team Model

2 Development Teams, 1 QA Team, & Shared Resources

Teams

Red Team

Claus Niesen (DM)

Brian Smith

Steve Manning

Jeff Ruch

Corey Pedersen


KRAD Phase 3
Screen Conversion

Shared Resources

Jessica Coltrin (PM)

Jerry Neal (KRAD Architect)

Matt Sargent (BA)

Tom Clark (UX)

Eric Westfall (LTA)

TBA (TW)