Overview
Timeline: Proposed 9 month release (~ 1/15/13-9/15/13)
Split: 68% new features/32% maintenance
Roadmap Items
- KRRM-144: KRAD Equivalency with KNS: 500 hours
- KRRM-141: KRAD Phase 3: 1000 hours
- KRRM-138: effective dating for KIM: 500 hrs
- KRRM-32: Mobile Application Support: 1000 hours
- KRRM-90: Add support in Rice for Document Management System: 500 hours
- KRRM-139: Offer RESTful Services from Rice: 800 hours (updated, was 200 hours during voting)
- KRRM-12: Implement Escalation Functionality: 200 hours
Roadmap Analysis & Development Hours: 4500
Documentation, Testing, Bug Fixing: 4110 hours (2940 dev hours, 1170 QA hours)
Total: 8610 hours
** Note: we may be able to get KRRM-1 - Implement JPA in if the POC work pans out as expected. The current thinking is once the POC work is done for KRAD as part of KRRM-137, it should be a short path to bring that back in. Should it also be on the Roadmap or can we wait to decide until analysis is complete? Perhaps list as a tentative roadmap item?
Maintenance Items
- Regression Testing (1170 QA hours)
- Critical Bug Fixing & Small Improvements, Reviewing & Incorporating Contributions (2940 Development Hours)
- Updating Outdated Documentation (TBD when tech writer is hired)
Total: 4110 Hours
Parallel Team Model
- 3 Development Teams, 1 QA Team, & Shared Resources
Teams
Erik Meade (Lead) |
Jessica Coltrin (PM) |
Matt Sargent (BA) |
Tom Clark (UX) |
Eric Westfall (LTA) |
TBA (TW) |