h2. Overview

*Timeline*:Milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release. Due to KS needs and ARC Approval, the scope of 2.3 was split into 2.3 and 2.4.

...






*Split*: ~ 70% new features/30%

...

Roadmap Items

 maintenance


h2. Roadmap Items

# [KRRM-144|https://jira.kuali.org/browse/KRRM-144]: KRAD Equivalency with KNS: delivered in 2.4, some items will be delivered in 2.3.

...


# [KRRM-141|https://jira.kuali.org/browse/KRRM-141]: KRAD Phase 3: 1000 hours; remaining items in 2.4

...


# [KRRM-143|https://jira.kuali.org/browse/KRRM-143]: Update delivered Rice Screens to use KRAD: delivered in 2.4, some screen conversions may be delivered in 2.3

...


# [KRRM-1|https://jira.kuali.org/browse/KRRM-1]: Implement JPA: delivered in 2.4

...




See [KULRICE:Rice 2.3 Design and Analysis] and [KULRICE:Rice 2.4 Design and Analysis] pages for more detailed analysis of Roadmap items.

...



See working [2.3 Project Schedule|https://docs.google.com/a/kuali.org/spreadsheet/ccc?key=0At8dhdqKa_2hdGNfTEFUZk5lemNwdUc2Q1NpXzhrWkE#gid=0] for task breakdown and detailed estimates.

...

Maintenance Items

  • Regression Testing
  • Critical Bug Fixing, Reviewing & Incorporating Contributions
  • Updating Outdated Documentation
  • Gap Analysis with KC & KFS on KNS/KRAD

Total: 2380 Hours

Bigger Maintenance Issues

KULRICE-7998

KULRICE-7991

KULRICE-8630

KULRICE-8631

Parallel Team Model

2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources

Teams

Section
Column
width20%
Panel
bgColor#F6E9E8
titleRed Team
Column
width20%
Panel
bgColor#dbe9f1
titleBlue Team
Column
width20%
Panel
bgColor#ffffcc
titleQA Team
Column
width20%
Panel
bgColor#ffebcd
titleJPA Team
Column
width20%
Panel
bgColor#99EBC2
titleShared Resources

Jessica Coltrin (PM)

Jerry Neal (KRAD Architect)

Functional Team: Matt Sargent (BA), Tom Clark (UX), Grant Trudel (TW)

Responsibilities

  • KNS Equivalency - Red Team, Jerry (some), Jonathan (analysis)
  • Rice Conversion, KRAD Phase 3 - Blue Team, Jerry (some)
  • JPA - JPA Team
  • 2.3 Maintenance Items - Jerry, others as needed
  • Testing, Performance Benchmarking - QA Team
  • Documentation Updates, Conversion Guide - Grant
  • KRAD Look & Feel, Screen Mocks/UX - Tom
  • Project Schedule/Coordination - Jessica
  • Requirements Prioritization & Analysis - Matt

Milestones

2.3 Milestone 1 Release - April 8, 2013

  • Screen Conversion: Misc. Cleanup, start on items delivered in m2
  • Phase 3: Page Titling redesign, Back button support for js actions, Iterate on validation framework UI (priority #2,5,6); Note that Breadcrumbs was postponed due to delays in requirements from KS

2.3 Milestone 2 Release - May 6, 2013

  • KRAD/KNS Equivalency: Session Support
  • Screen Conversion: Login Page, Action List
  • Phase 3: KULRICE-8630 (History and Breadcrumbs), Improved Session Support, some performance enhancement

2.3 Milestone 3 Release - June 10, 2013

  • KRAD/KNS Equivalency: Lookup & Multi-value Lookup (incl. conversion guide and script), Inquiry gap analysis, Finish Removing Struts, Module Support (MVC)
  • Screen Conversion: Main Menu - Sample Travel Application Channel, Workflow, Notification, Document Search
  • Phase 3: Improve Performance & Memory Consumption (priority #1,3,4)
  • Bootstrap & LESS

2.3 Final Release - July 31, 2013

  • Regression Testing 
  • Testing & Documentation of new Features

2.4 Milestone 1 Release - August 12, 2013

  • KRAD/KNS Equivalency: Inquiry (incl. conversion guide and script), Maintenance gap analysis, Components/Collections,Security, Presentation and Authorizer
  • Phase 3:
  • Screen Conversion: Main Menu - KRMS Rules, Administration - Workflow, Notification
  • JPA: Data Layer Restructuring, Internal JPA Conversion, JPA Conversion Support

2.4 Milestone 2 - September 16, 2013

  • KRAD/KNS Equivalency: Maintenance (incl. conversion guide and script), Transactional gap analysis
  • Screen Conversion: Administration - Identity, Configuration

2.4 Milestone 3 - October 14, 2013

  • KRAD/KNS Equivalency: Transactional(incl. conversion guide and script), Complete Draft of Conversion Scripts & Guide
  • Screen Conversion: Administration - Service Bus, Miscellaneous
  • Online Help integrated with DocBook & documented for project use

2.4 Final Release - November 1, 2013

...





h2. Maintenance Items

* Regression Testing
* Critical Bug Fixing, Reviewing & Incorporating Contributions
* Updating Outdated Documentation
* Gap Analysis with KC & KFS on KNS/KRAD

*Total*: 2380 Hours

h4. Bigger Maintenance Issues

*KULRICE-7998*

*KULRICE-7991*

*KULRICE-8630*

*KULRICE-8631*

h2. Parallel Team Model

2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources


*Teams*

{section}
{column:width=20%}
{panel:title=Red Team|bgColor=#F6E9E8}
| [~cniesen] (DM) |
| [~samuel] |
| [~sdm86] |
| [~mztaylor] |
| [~shahess] |
{panel}
{column}
{column:width=20%}
{panel:title=Blue Team|bgColor=#dbe9f1}
| [~gilesp] (DM) |
| [~bsmith] |
| [~jruch] |
| [Sona Muthuswamy|~sonam] |
| [~cpedersen] |
| [~matthew.wuertz] |
{panel}
{column}
{column:width=20%}
{panel:title=QA Team|bgColor=#ffffcc}
| [Erik Meade |~eghm-kuali-m] (Lead) |
| [~mmodi] |
| [~vchauhan] |
{panel}
{column}
{column:width=20%}
{panel:title=JPA Team|bgColor=#ffebcd}
| [Eric Westfall |~eghm-kuali-m] (LTA) |
| [~ahamid] |
| [~jkeller] |
{panel}
{column}
{column:width=20%}
{panel:title=Shared Resources|bgColor=#99EBC2}
| [~jcoltrin] (PM) \\ |
| [~jkneal] (KRAD Architect) \\ |
| *Functional Team*: [~masargen] (BA), [~thrclark] (UX), [Grant Trudel|~gptrude] (TW) |
{panel}
{column}
{section}

h2. Responsibilities



* *KNS Equivalency* \- Red Team, Jerry (some), Jonathan (analysis)
* *Rice Conversion, KRAD Phase 3* \- Blue Team, Jerry (some)
* *JPA* \- JPA Team
* *2.3 Maintenance Items* \- Jerry, others as needed
* *Testing, Performance Benchmarking* \- QA Team
* *Documentation Updates, Conversion Guide* \- Grant
* *KRAD Look & Feel, Screen Mocks/UX* \- Tom
* *Project Schedule/Coordination -* Jessica
* *Requirements Prioritization & Analysis* \- Matt





h2. Milestones


h3. 2.3 Milestone 1 Release - April 8, 2013

* Screen Conversion: Misc. Cleanup, start on items delivered in m2
* Phase 3: Page Titling redesign, Back button support for js actions, Iterate on validation framework UI (priority #2,5,6); Note that Breadcrumbs was postponed due to delays in requirements from KS


h3. 2.3 Milestone 2 Release - May 6, 2013

* KRAD/KNS Equivalency: Session Support
* Screen Conversion: Login Page, Action List
* Phase 3: KULRICE-8630 (History and Breadcrumbs), Improved Session Support, some performance enhancement


h3. 2.3 Milestone 3 Release - June 10, 2013

* KRAD/KNS Equivalency: Lookup & Multi-value Lookup (incl. conversion guide and script), Inquiry gap analysis, Finish Removing Struts, Module Support (MVC)
* Screen Conversion: Main Menu - Sample Travel Application Channel, Workflow, Notification, Document Search
* Phase 3: Improve Performance & Memory Consumption (priority #1,3,4)
* Bootstrap & LESS


h3. 2.3 Final Release - July 31, 2013

* Regression Testing 
* Testing & Documentation of new Features

----
h3. 2.4 Milestone 1 Release - August 12, 2013

* KRAD/KNS Equivalency: Inquiry (incl. conversion guide and script), Maintenance gap analysis, Components/Collections,Security, Presentation and Authorizer
* Phase 3:
* Screen Conversion: Main Menu - KRMS Rules, Administration - Workflow, Notification
* JPA: Data Layer Restructuring, Internal JPA Conversion, JPA Conversion Support



h3. 2.4 Milestone 2 - September 16, 2013

* KRAD/KNS Equivalency: Maintenance (incl. conversion guide and script), Transactional gap analysis
* Screen Conversion: Administration - Identity, Configuration

h3. 2.4 Milestone 3 - October 14, 2013

* KRAD/KNS Equivalency: Transactional(incl. conversion guide and script), Complete Draft of Conversion Scripts & Guide
* Screen Conversion: Administration - Service Bus, Miscellaneous
* Online Help integrated with DocBook & documented for project use



h3. 2.4 Final Release - November 1, 2013

* Regression Testing
* Complete Unit & Integration Tests
* Complete Performance Testing
* Complete Documentation