Table of Contents |
---|
Overview
...
Wiki Markup |
---|
{toc} h2. Overview *Timeline*:Milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release. Due to KS needs and ARC Approval, the scope of 2.3 was split into 2.3 and 2.4. |
...
*Split*: ~ 70% new features/30% |
...
Roadmap Items
maintenance h2. Roadmap Items # [KRRM-144|https://jira.kuali.org/browse/KRRM-144]: KRAD Equivalency with KNS: delivered in 2.4, some items will be delivered in 2.3. |
...
# [KRRM-141|https://jira.kuali.org/browse/KRRM-141]: KRAD Phase 3: 1000 hours; remaining items in 2.4 |
...
# [KRRM-143|https://jira.kuali.org/browse/KRRM-143]: Update delivered Rice Screens to use KRAD: delivered in 2.4, some screen conversions may be delivered in 2.3 |
...
# [KRRM-1|https://jira.kuali.org/browse/KRRM-1]: Implement JPA: delivered in 2.4 |
...
See [KULRICE:Rice 2.3 Design and Analysis] and [KULRICE:Rice 2.4 Design and Analysis] pages for more detailed analysis of Roadmap items. |
...
See working [2.3 Project Schedule|https://docs.google.com/a/kuali.org/spreadsheet/ccc?key=0At8dhdqKa_2hdGNfTEFUZk5lemNwdUc2Q1NpXzhrWkE#gid=0] for task breakdown and detailed estimates. |
...
Maintenance Items
- Regression Testing
- Critical Bug Fixing, Reviewing & Incorporating Contributions
- Updating Outdated Documentation
- Gap Analysis with KC & KFS on KNS/KRAD
Total: 2380 Hours
Bigger Maintenance Issues
KULRICE-7998
KULRICE-7991
KULRICE-8630
KULRICE-8631
Parallel Team Model
2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources
Teams
Section | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Responsibilities
- KNS Equivalency - Red Team, Jerry (some), Jonathan (analysis)
- Rice Conversion, KRAD Phase 3 - Blue Team, Jerry (some)
- JPA - JPA Team
- 2.3 Maintenance Items - Jerry, others as needed
- Testing, Performance Benchmarking - QA Team
- Documentation Updates, Conversion Guide - Grant
- KRAD Look & Feel, Screen Mocks/UX - Tom
- Project Schedule/Coordination - Jessica
- Requirements Prioritization & Analysis - Matt
Milestones
2.3 Milestone 1 Release - April 8, 2013
- Screen Conversion: Misc. Cleanup, start on items delivered in m2
- Phase 3: Page Titling redesign, Back button support for js actions, Iterate on validation framework UI (priority #2,5,6); Note that Breadcrumbs was postponed due to delays in requirements from KS
2.3 Milestone 2 Release - May 6, 2013
- KRAD/KNS Equivalency: Session Support
- Screen Conversion: Login Page, Action List
- Phase 3: KULRICE-8630 (History and Breadcrumbs), Improved Session Support, some performance enhancement
2.3 Milestone 3 Release - June 10, 2013
- KRAD/KNS Equivalency: Lookup & Multi-value Lookup (incl. conversion guide and script), Inquiry gap analysis, Finish Removing Struts, Module Support (MVC)
- Screen Conversion: Main Menu - Sample Travel Application Channel, Workflow, Notification, Document Search
- Phase 3: Improve Performance & Memory Consumption (priority #1,3,4)
- Bootstrap & LESS
2.3 Final Release - July 31, 2013
- Regression Testing
- Testing & Documentation of new Features
2.4 Milestone 1 Release - August 12, 2013
- KRAD/KNS Equivalency: Inquiry (incl. conversion guide and script), Maintenance gap analysis, Components/Collections,Security, Presentation and Authorizer
- Phase 3:
- Screen Conversion: Main Menu - KRMS Rules, Administration - Workflow, Notification
- JPA: Data Layer Restructuring, Internal JPA Conversion, JPA Conversion Support
2.4 Milestone 2 - September 16, 2013
- KRAD/KNS Equivalency: Maintenance (incl. conversion guide and script), Transactional gap analysis
- Screen Conversion: Administration - Identity, Configuration
2.4 Milestone 3 - October 14, 2013
- KRAD/KNS Equivalency: Transactional(incl. conversion guide and script), Complete Draft of Conversion Scripts & Guide
- Screen Conversion: Administration - Service Bus, Miscellaneous
- Online Help integrated with DocBook & documented for project use
2.4 Final Release - November 1, 2013
...
h2. Maintenance Items * Regression Testing * Critical Bug Fixing, Reviewing & Incorporating Contributions * Updating Outdated Documentation * Gap Analysis with KC & KFS on KNS/KRAD *Total*: 2380 Hours h4. Bigger Maintenance Issues *KULRICE-7998* *KULRICE-7991* *KULRICE-8630* *KULRICE-8631* h2. Parallel Team Model 2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources *Teams* {section} {column:width=20%} {panel:title=Red Team|bgColor=#F6E9E8} | [~cniesen] (DM) | | [~samuel] | | [~sdm86] | | [~mztaylor] | | [~shahess] | {panel} {column} {column:width=20%} {panel:title=Blue Team|bgColor=#dbe9f1} | [~gilesp] (DM) | | [~bsmith] | | [~jruch] | | [Sona Muthuswamy|~sonam] | | [~cpedersen] | | [~matthew.wuertz] | {panel} {column} {column:width=20%} {panel:title=QA Team|bgColor=#ffffcc} | [Erik Meade |~eghm-kuali-m] (Lead) | | [~mmodi] | | [~vchauhan] | {panel} {column} {column:width=20%} {panel:title=JPA Team|bgColor=#ffebcd} | [Eric Westfall |~eghm-kuali-m] (LTA) | | [~ahamid] | | [~jkeller] | {panel} {column} {column:width=20%} {panel:title=Shared Resources|bgColor=#99EBC2} | [~jcoltrin] (PM) \\ | | [~jkneal] (KRAD Architect) \\ | | *Functional Team*: [~masargen] (BA), [~thrclark] (UX), [Grant Trudel|~gptrude] (TW) | {panel} {column} {section} h2. Responsibilities * *KNS Equivalency* \- Red Team, Jerry (some), Jonathan (analysis) * *Rice Conversion, KRAD Phase 3* \- Blue Team, Jerry (some) * *JPA* \- JPA Team * *2.3 Maintenance Items* \- Jerry, others as needed * *Testing, Performance Benchmarking* \- QA Team * *Documentation Updates, Conversion Guide* \- Grant * *KRAD Look & Feel, Screen Mocks/UX* \- Tom * *Project Schedule/Coordination -* Jessica * *Requirements Prioritization & Analysis* \- Matt h2. Milestones h3. 2.3 Milestone 1 Release - April 8, 2013 * Screen Conversion: Misc. Cleanup, start on items delivered in m2 * Phase 3: Page Titling redesign, Back button support for js actions, Iterate on validation framework UI (priority #2,5,6); Note that Breadcrumbs was postponed due to delays in requirements from KS h3. 2.3 Milestone 2 Release - May 6, 2013 * KRAD/KNS Equivalency: Session Support * Screen Conversion: Login Page, Action List * Phase 3: KULRICE-8630 (History and Breadcrumbs), Improved Session Support, some performance enhancement h3. 2.3 Milestone 3 Release - June 10, 2013 * KRAD/KNS Equivalency: Lookup & Multi-value Lookup (incl. conversion guide and script), Inquiry gap analysis, Finish Removing Struts, Module Support (MVC) * Screen Conversion: Main Menu - Sample Travel Application Channel, Workflow, Notification, Document Search * Phase 3: Improve Performance & Memory Consumption (priority #1,3,4) * Bootstrap & LESS h3. 2.3 Final Release - July 31, 2013 * Regression Testing * Testing & Documentation of new Features ---- h3. 2.4 Milestone 1 Release - August 12, 2013 * KRAD/KNS Equivalency: Inquiry (incl. conversion guide and script), Maintenance gap analysis, Components/Collections,Security, Presentation and Authorizer * Phase 3: * Screen Conversion: Main Menu - KRMS Rules, Administration - Workflow, Notification * JPA: Data Layer Restructuring, Internal JPA Conversion, JPA Conversion Support h3. 2.4 Milestone 2 - September 16, 2013 * KRAD/KNS Equivalency: Maintenance (incl. conversion guide and script), Transactional gap analysis * Screen Conversion: Administration - Identity, Configuration h3. 2.4 Milestone 3 - October 14, 2013 * KRAD/KNS Equivalency: Transactional(incl. conversion guide and script), Complete Draft of Conversion Scripts & Guide * Screen Conversion: Administration - Service Bus, Miscellaneous * Online Help integrated with DocBook & documented for project use h3. 2.4 Final Release - November 1, 2013 * Regression Testing * Complete Unit & Integration Tests * Complete Performance Testing * Complete Documentation |