Table of Contents |
---|
Overview
Timeline:Milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release. Due to KS needs and ARC Approval, the scope of Original scope for 2.3 was has been split into 3 minor releases: Rice 2.3 and , Rice 2.4, and Rice 2.5.
Split: ~ 70% new features/30% maintenance
Scope & Tasks
See working 2.3 Project Plan spreadsheet for task breakdown, tracking, and progress.
Roadmap Items
...
Original scope for 2.3 has been split into 3 minor releases: Rice 2.3, Rice 2.4, and Rice 2.5.
Roadmap Items
- KRRM-141: KRAD Phase 3: top 5 items
See Rice 2.3 Design and Analysis and Rice 2.4 Design and Analysis pages page for more detailed analysis of Roadmap items.
Resources
Parallel Team Model: 2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources
Teams
Section | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Responsibilities
- KNS Equivalency - Red Team, Jerry (some), Jonathan (analysis)
- Rice Conversion, KRAD Phase 3 - Blue Team, Jerry (some)
- JPA - JPA Team
- 2.3 Maintenance Items - Jerry, others as needed
- Testing, Performance Benchmarking - QA Team
- Documentation Updates, Conversion Guide - Grant
- KRAD Look & Feel, Screen Mocks/UX - Tom
- Project Schedule/Coordination - Jessica
- Requirements Prioritization & Analysis - Matt
Milestones
2.3 Milestone 1 Release - April 8, 2013
- Screen Conversion: Misc. Cleanup, start on items delivered in m2
- Phase 3: Page Titling redesign, Back button support for js actions, Iterate on validation framework UI (priority #2,5,6); Note that Breadcrumbs was postponed due to delays in requirements from KS
2.3 Milestone 2 Release - May 6, 2013
- KRAD/KNS Equivalency: Session Support
- Screen Conversion: Login Page
- Phase 3: KULRICE-8630 (History and Breadcrumbs), Improved Session Support, some performance enhancements including lite table
2.3 Milestone 3 Release - June 24, 2013
- KRAD/KNS Equivalency: Lookup (except Multi-Value Lookup)
- Screen Conversion: Action List
- Phase 3: Improve Performance & Memory Consumption (priority #1,3,4)
- Inclusion of Bootstrap & LESS
2.3 Release Candidate 1 - July 8, 2013
- Bootstrap/LESS themes
- Tier 2 Performance Enhancements
2.3 Final Release - July 31, 2013
- Regression Testing
- Testing & Documentation of new Features
- Bug Fixes
2.4 Milestone 1 Release - August 12, 2013
- KRAD/KNS Equivalency: Multi-value Lookup , Inquiry gap analysis, Finish Removing Struts, Module Support (MVC), Inquiry, Maintenance gap analysis, Components/Collections,Security, Presentation and Authorizer
- Phase 3:
- JPA: Data Layer Restructuring, Internal JPA Conversion, JPA Conversion Support
2.4 Milestone 2 - September 16, 2013
- KRAD/KNS Equivalency: Maintenance (incl. conversion guide and script), Transactional gap analysis
- Screen Conversion: Administration - Identity, Configuration
2.4 Milestone 3 - October 14, 2013
- KRAD/KNS Equivalency: Transactional(incl. conversion guide and script), Complete Draft of Conversion Scripts & Guide
- Online Help integrated with DocBook & documented for project use
2.4 Final Release - February 15, 2014
- Regression Testing
- Complete Unit & Integration Tests
- Complete Performance Testing
- Complete Documentation
2.5 Final Release - August 2014
- screen conversions