Overview

Timeline: Proposed 6 month release (~ 1/15/13-7/15/13) with milestones Milestones every 4-5 weeks or so. Technical Analysis indicated more of a 9 month release. Original scope for 2.3 has been split into 3 minor releases: Rice 2.3, Rice 2.4, and Rice 2.5.

Split: ~ 70% new features/30% maintenance

Scope & Tasks

See working 2.3 Project Plan spreadsheet for task breakdown, tracking, and progress. Original scope for 2.3 has been split into 3 minor releases: Rice 2.3, Rice 2.4, and Rice 2.5.

Roadmap Items

...

  1. KRRM-144: KRAD Equivalency with KNS: 500 hoursKRRM-141: KRAD Phase 3: 1000 hours
  2. KRRM-143: Update delivered Rice Screens to use KRAD: 1000 hours
  3. KRRM-1: Implement JPA: 1000 hours

Roadmap Analysis & Development Hours: 3500
Gap Analysis with KC & KFS on KNS/KRAD: 400 hours
Documentation, Testing, Bug Fixing: 2380 hours (1600 dev hours, 780 QA hours)
Total: 6280 hours

...

  1. top 5 items

See Rice 2.3 Design and Analysis page  page for more detailed analysis of Roadmap items.

See working 2.3 Project Schedule for task breakdown and detailed estimates.

Maintenance Items

  • Regression Testing (780 QA hours)
  • Critical Bug Fixing, Reviewing & Incorporating Contributions (1600 Development Hours)
  • Updating Outdated Documentation (TBD when tech writer is hired)

Total: 2380 Hours

Bigger Maintenance Issues

KULRICE-7998

KULRICE-7991

KULRICE-8630

KULRICE-8631

Resources

Parallel Team Model

...

: 2 Development Teams, 1 JPA Task Force, 1 QA Team, & Shared Resources

Teams

Section
Column
width20%
Panel
bgColor#F6E9E8
titleRed Team
Column
width20%
Panel
bgColor#dbe9f1
titleBlue Team
Column
width20%
Panel
bgColor#ffffcc
titleQA Team

Erik Meade (Lead)

Mayank Modi

Viral Chauhan Dan Seibert

Deep Moteria

Column
width20%
Panel
bgColor#ffebcd
titleJPA Team
Column
width20%
Panel
bgColor#99EBC2
titleShared Resources

Jessica Coltrin (PM)

Jerry Neal (KRAD Architect)

Functional Team: Matt Sargent (BA), Tom Clark (UX), Grant Trudel (TW)

...

Responsibilities

  • KNS Equivalency

...

  •  - Red Team, Jerry (some), Jonathan (

...

  • analysis)
  • Rice Conversion, KRAD Phase 3

...

  •  - Blue Team, Jerry (some)
  • JPA

...

  •  - JPA Team

Milestones

Milestone 1 Release - March 4, 2013

  • KRAD/KNS Equivalency: Lookup, Inquiry, Session Support
  • Screen Conversion: Login Page, Document Search, Action List, Help
  • Phase 3: 
  • Maintenance (Big): KULRICE-8630 (History and Breadcrumbs)
  • JPA: Data Layer Restructuring

...

  • 2.3 Maintenance Items - Jerry, others as needed
  • Testing, Performance Benchmarking - QA Team
  • Documentation Updates, Conversion Guide - Grant
  • KRAD Look & Feel, Screen Mocks/UX - Tom
  • Project Schedule/Coordination - Jessica
  • Requirements Prioritization & Analysis - Matt

Milestones

2.3 Milestone 1 Release - April 8, 2013

  • KRAD/KNS Equivalency: Maintenance, Transactional, Security, Presentation and Authorizer
  • Screen Conversion: Main Menu - Sample Travel Application Channel, Workflow, NotificationMisc. Cleanup, start on items delivered in m2
  • Phase 3:
  • Maintenance (Big):
  • JPA: Internal JPA Conversion, JPA Conversion Support

...

  • Page Titling redesign, Back button support for js actions, Iterate on validation framework UI (priority #2,5,6); Note that Breadcrumbs was postponed due to delays in requirements from KS

2.3 Milestone 2 Release - May 6, 2013

  • KRAD/KNS Equivalency: Finish Removing Struts, Components/Collections, Module Support (MVC)Session Support
  • Screen Conversion: Main Menu - KRMS Rules, Administration - Workflow, NotificationLogin Page
  • Phase 3:
  • Maintenance (Big):
  • JPA: Test & Merge JPA code

...

  • KULRICE-8630 (History and Breadcrumbs), Improved Session Support, some performance enhancements including lite table

2.3 Milestone 3 Release - June 24, 2013

  • KRAD/KNS Equivalency: Complete Draft of Conversion Scripts & Guide
  • Phase 3:
  • Maintenance (Big):Lookup (except Multi-Value Lookup) 
  • Screen Conversion: Administration - Identity, Configuration

Milestone 5 - July 8, 2013

  • Screen Conversion: Administration - Service Bus, Miscellaneous

Milestone 6 - August 12, 2013

Milestone 7 - September 16, 2013

RC1 Release - October 14, 2013

  • Complete Unit & Integration Tests
  • Complete Performance Testing

Final Release - November 1, 2013

  • Action List
  • Phase 3: Improve Performance & Memory Consumption (priority #1,3,4)
  • Inclusion of Bootstrap & LESS

2.3 Release Candidate 1 - July 8, 2013

  • Bootstrap/LESS themes
  • Tier 2 Performance Enhancements

2.3 Final Release - July 31, 2013

  • Regression Testing 
  • Testing & Documentation of new Features
  • Bug Fixes