  • 2.4.0-m3 Sprint 1 
  • 2.4.0-m3 Sprint 2 
  • 2.4.0-m3 Sprint 3
  • 2.4.0-m4 Sprint 4

2.4 Milestone 4 - February

...

19, 2014 - complete

Scope:

  • KRAD/KNS Equivalency:  
    • Focus Groups for Components 
    • Finish Conversion Script & Guide for 2.4 (tick)
    • Work on non-UXI gap items (tick)
  • JPA:
    • KIM, KRMS,KEN Converted to JPA (tick)
    • Conversion script documentation (tick)
    • Mostly completed Documentation 
  • QA: 
    • Establish performance testing plan (tick)
    • Set up dedicated performance test environment (tick)

...