Scope & Tasks
See working 2.4 Agile Planning Board for task breakdown, tracking, and progress.
Items
-
-
- (possibly out of scope)
See Rice 2.4 Design and Analysis pages for more detailed analysis of Roadmap items.
Milestones
2.4 Milestone 1 - August 12, 2013 - complete
Scope:
- JPA: Data Layer Restructuring, some Internal JPA Conversion
Sprints:
- JPA Sprint 1
- JPA Sprint 2
- JPA Sprint 3
- JPA Sprint 4
- JPA Sprint 5
2.4 Milestone 2 - October 15, 2013 - complete
Scope:
- KRAD/KNS Equivalency:
- Lookup Gap Analysis complete (Phases 1 & 2 - identification of items & if they're already covered in KRAD)
- Inquiry Gap Analysis complete for Inquiry
- Maintenance Gap Analysis complete for Maintenance
- Lookup Equivalency achieved (jiras done)
- Lookup Conversion Guide draft complete
- Lookup Phase 3 Analysis (focus group preparation & review)
- Lookup Gap Analysis complete (Phases 1 & 2 - identification of items & if they're already covered in KRAD)
- JPA:
- Internal conversion of KEW to JPA
- "Defaulting" features for inquiries, lookups, etc. (needed for demo at Kuali Days!)
- Internal conversion of KEW to JPA
- KRAD Phase 3:
- Performance tuning goals for response time
- Performance tuning goals for response time
- UXI
- Application Header
- New Left Menu
- Form Control redesign
- Input Groups
- Label Align CSS Grid
- Styling improvements: View Header, Sticky Footer, Tabs, Disclosures, Dialogs
- QA:
Sprints:
- 2.4.0-m2 Sprint 1
- 2.4.0-m2 Sprint 2
- 2.4.0-m3 Sprint 3
- 2.4.0-m3 Sprint 4
2.4 Milestone 3 - December 17, 2013 - complete
Scope:
- KRAD/KNS Equivalency:
- Review of Inquiry
Focus Groups for Inquiry (Peter)
Sample App buildout for Inquiry
Conversion Guide - Documentation of change in how to do something in KRAD vs. KNS for non-gaps for Inquiry, Data Dictionary, Maintenance
- Finish Lookup, Inquiry, Data Dictionary, Conversion Script and Guide
- Review of Maintenance, Data Dictionary
- Focus Groups for Maintenance, Data Dictionary
- Sample App buildout for Maintenance
- Review of Inquiry
- JPA:
- eDocLite converted to JPA
- KSB converted to JPA
- Basic documentation on how to convert OJB to JPA
- Conversion scripts for OJB to JPA
- eDocLite converted to JPA
- KRAD Phase 3:
- Performance: DOM cleanup & memory work
- Implement DevOps Database Process Changes
- QA:
- Formalize strategy for JPA testing
- Establish performance testing plan
- AFT Gap Analysis: Continue with gap analysis on granular level to confirm that existing tests perform as they should
- Continued JIRA backlog grooming
- Close manually-testable Resolved jiras
- Continue to fill AFT gaps (with JPA testing strategy in mind)
- Formalize strategy for JPA testing
- KD Prep
Sprints:
- 2.4.0-m3 Sprint 1
- 2.4.0-m3 Sprint 2
- 2.4.0-m3 Sprint 3
- 2.4.0-m4 Sprint 4
2.4 Milestone 4 - February 19, 2014 - complete
Scope:
- KRAD/KNS Equivalency:
- Focus Groups for Components
- Finish Conversion Script & Guide for 2.4
- Work on non-UXI gap items
- JPA:
- KIM, KRMS,KEN Converted to JPA
- Conversion script documentation
- Mostly completed Documentation
- KIM, KRMS,KEN Converted to JPA
- QA:
- Establish performance testing plan
- Set up dedicated performance test environment
- Establish performance testing plan
Sprints:
- 2.4.0-m4 Sprint 1
- 2.4.0-m4 Sprint 2
- 2.4.0-m4 Sprint 3
- 2.4.0-m4 Sprint 4
2.4 Final Release - April 18, 2014
Scope:
- Complete Regression Testing
- Complete Unit & Integration Tests
- Complete Performance Testing
- Complete Documentation