Gliffy Zoom Zoom Rice 2.2 Timeline

Requirements

Rice 2.2 contains the following Roadmap Items

For more details Rice 2.2 - KRAD Requirements.

Upcoming Milestones

Final Release - December 3, 2012

  • bug fixes, documentation

Released Milestones

Milestone 1 - Feb. 27 - May 14, 2012 - RELEASED

View full list of m1 items in Jira

Feature

Complete?

Notes

Performance Improvements (Req #1)

(tick)

 

Framework Code Improvements (Req #2)

(tick)

 

Legend tag for fieldsets (Req #23)

(tick)

 

Validation Message refactoring for Accessibility (Req #3)

(tick)

 

Tooltip  (Req #4)

(tick)

 

Help Framework (needed for KNS Equivalence) (Req #5)

(tick)

originally a m2 item, was completed early

Note: Assume majority of performance work completed here.

Milestone 2 - May 14 - July 18, 2012 (~7 weeks) - RELEASED

View full list of m2 items in Jira

Feature

Estimate

Complete

Note

Performance Improvements (Req #1)

30 hrs

(tick)

 

Framework Code Improvements (Req #2) - Ajax Improvements

50 hrs

(tick)

 

Question Framework - configurable modal dialog box (needed for KNS Equivalence) - see also #11 below. (Req #6)

90 hrs

(tick)

 

General Lightbox Div Content - (this is the UI aspect of the question framework item above - that one is the backend aspect) (Req #11)

 

(tick)

 

State-based validation (Req #9)

 

(tick)

 

Collections re-design: Add collection button adds line with blank fields, user enters data in fields, no additional add action needed (Req #24)

 

(tick)

 

Collections re-design: Add collection item via lightbox (or other) (Req #25)

 

(tick)

 

Collections re-design: action field column placement (left or right) configurable (Req #26)

 

(tick)

 

Collections re-design: Yellow highlighting on new collection items (until submit) - & maybe when hovering on delete function (Req #27)

 

(tick)

 

Master detail relationship within a table (Req #30)

10 hrs

(tick)

 

Merge of all 2.1 features (and bug fixes) - see Rice 2.1 Project Plan with Milestones for details

 

(tick)

 

Rice Data Objects (RDO) Tooling (Req #12)

 

(tick)

 

Milestone 3 - August 24, 2012 - RELEASED

Milestone 3 is essentially m2 functionality plus bug fixes and performance enhancements needed for KS My Plan soft launch.

Milestone 4 - July 18, 2012 - October 1st, 2012 - RELEASED

View full list of m3 items in Jira

Feature

Estimate

Complete

Note

Lead

Collections: Total Lines and Grouping   (Req #28)

50 hours

(tick)

 

Samuel

Messages from Central Repository (Req #7)

30 hours

(tick)

 

Jerry

Rich Messages (Req #8)

 

(tick)

 

Brian

Access (view only) without authenticating into portal (Req #10)

2 hours

(tick)

 

Jerry

Evaluate KS My Plan contributions for incorporation: (maintenance time)
- CONTRIB-52: Component refresh from content outside of the containing Form
- CONTRIB-53: Event driven component updates on the client side

1 hour

(tick)

 

Team

Rice Dictionary Validator (RDV) Tooling

 

(tick)

 

Cody

Note: For this milestone maintenance work will focus on the following items:

  • Transactional Document Support
  • Dialog/Lightbox (some small enhancements/cleanup from m2)
  • Master/Detail (some small enhancements/cleanup from m2)
  • Ajax Improvements (some small enhancements/cleanup from m2)

Milestone 5 - November 6th, 2012

  • Bug Fixes needed for My Plan, documentation

Release Candidate 1 - November 23rd, 2012

  • KS-KRMS changes
  • should include transactional document support
  • bug fixes, documentation